NORDPARK CABLE RAILWAY - ZAHA HADID ARCHITECTS: PROJECT DATA
PROJECT START DATE: December 2004
START ON SITE DATE: December 2005
DATE OF COMPLETION: December 2007
Architect: Zaha Hadid Architects
Design: Zaha Hadid with Patrik Schumacher
Project Architect: Thomas Vietzke
Design Team:Jens Borstelmann/Markus Planteu
Production Team:Caroline Andersen/Makakrai Suthadarat/Marcela Spadaro/Anneka Wagener/Adriano di Gionnis/Peter Pichler/Susann Berggren
Local Partner: Malojer Baumanagement GmbH
Planning Adviser: ILF Beratende Ingenieure ZT
Contractor: Strabag AG
Engines & Cables Contractor: Leitner GmbH
Facade Contractor: Pagitz Metalltechnik GmbH
Structural Engineers (concrete base):Baumann & Obholzer Ziviltechniker
Structural Engineers (roof structure):Bollinger Grohmann Schneider ZT
Bridge/Track Engineer: ILF Beratende Ingenieure ZT
FORM OF CONTRACT: Public Private Partnership
TOTAL COST: Undisclosed
TOTAL ROOF SURFACE AREA (ALL STATIONS INCLUSIVE): 2,500M2
CONSTRUCTION MATERIALS: BASE – Reinforced Concrete
STRUCTURE – Steel
CLADDING – Thermoformed Glass
CLIENT: INKB (Innsbrucker Nordkettenbahnen GmbH) Public Private Partnership